Wynn Al Marjan Island Opening Delayed to September 2027, Budget Rises to $5.8 Billion

Wynn Resorts moved its UAE casino resort debut to September 2027 after regional supply disruptions, adding $600 million to the project cost.

Aerial view of a large construction site on a man-made peninsula featuring two tall concrete building towers surrounded by multiple cranes.

Wynn Resorts has revised the debut of Wynn Al Marjan Island, its resort under construction in Ras Al Khaimah, to September 2027. The company earlier pointed to a first-quarter 2027 start, but now attributes the later schedule to regional conflict that disrupted freight and supply lines. The shift added $600 million to the expected cost, bringing it to about $5.8 billion. Even with the new timing, the property remains on track to be the first licensed casino resort in the United Arab Emirates.

Why the opening date shifted

According to Covers Industry, the property initially had a tentative launch during the opening months of 2027. The fighting made sea transport unreliable, held up deliveries of construction supplies, and briefly interrupted activity at the site. The project sits on Al Marjan Island, a manufactured coastal development in the northern emirate. On a second-quarter earnings call, Chief Executive Craig Billings said the U.S.-Iran conflict hurt worldwide supply networks and kept raising costs for shipping insurance. He said certain materials and equipment had to be ordered from other sources, moved along different routes, or rushed ahead so the construction schedule would not slip further.

Budget increase and ownership structure

Wynn now expects the project to cost about $5.8 billion, up by $600 million. The company attributed around half of the added expense to the regional disruption, including higher logistics and building costs. It kept work moving by changing where it purchased supplies and using different delivery channels. Wynn owns 40 percent of the joint venture developing the property with Marjan and RAK Hospitality Holding. Card Player reported that the resort's final tab is now more than $5 billion.

Construction work and a single-phase opening

Billings told analysts that crews were already working on hotel rooms, while hiring and operations planning were also advancing. The property will not open in phases; all amenities are expected to be ready when the resort welcomes its first guests. Plans call for a 70-story building topped by a spire that rises 352 meters over the Gulf. The resort is designed to include more than 1,500 rooms and suites, restaurants, entertainment venues, luxury retail, beach facilities, a gaming space, a marina, private shoreline, and event areas. Billings described the project as unique in the region and said Wynn expected it to be one of the most significant integrated resort openings in more than a decade. He added that the company remained confident about the UAE.

Licensed casino position and tax outlook

In October 2024, the General Commercial Gaming Regulatory Authority granted Wynn the country's first commercial gaming permit. That made Wynn Al Marjan Island the UAE's first licensed casino resort. The property will pay a combined tax of 10 to 12 percent on gross gaming revenue, a rate similar to Singapore's. Wynn has projected that the UAE could become a $3 billion to $5 billion gross gaming revenue market once more operators enter, according to Card Player, citing a 2025 earnings call. The regulator's executive chairman, Jim Murren, has said he expects up to four casinos may eventually be built. Wynn therefore holds an early position in a new market even after the schedule change.